QUAY Construction

North Vancouver ensuite renovation with a freestanding soaker tub, glass walk-in shower and wood slat ceiling

North Vancouver Townhouse Bathroom Renovation Cost: What $128K Covered in Three Rooms

Three bathrooms in one North Vancouver townhouse came in at about $128,000 together when QUAY rebuilt them in 2023: about $67,000 for the master ensuite, about $39,000 for the main bathroom and about $22,000 for the powder room. Each room was planned as its own phase, with about two weeks of construction for the powder room and the main bathroom and about three weeks for the ensuite.

The home is in Northlands, on the Seymour side of the District of North Vancouver, and it makes a useful benchmark because it shows how far apart three rooms in the same house can land: the ensuite cost three times as much as the powder room. If you are planning bathrooms of your own on the North Shore, our bathroom renovation service in North Vancouver explains how we plan, price and permit them. This guide goes room by room through what each of these three budgets paid for, and why the numbers differ.

Every project figure below is the one published on the Northlands townhouse project page. Planning ranges come from our bathroom renovation cost guide.

The three budgets at a glance

RoomBudgetConstruction timeWhat it included
Master ensuiteAbout $67,000About three weeksNew framed wall behind the vanity, floating double vanity with vessel sinks, freestanding soaker tub, tiled walk-in shower with glass enclosure, NuHeat heated floor, wall-hung toilet, wood slat ceiling
Main bathroomAbout $39,000About two weeksBulkhead and popcorn ceiling removed, new tiled shower with linear drain, fluted wood-look wall tile, NuHeat heated floor, white oak vanity with quartz top, wallpaper
Powder roomAbout $22,000About two weeksTaken back to the studs, wood slat feature wall, wall-hung toilet with in-wall tank, green tile wainscot, floating vanity with vessel sink
All threeAbout $128,000Phased, room by roomCompleted in 2023 with a 365-day workmanship warranty

Construction times are on site, after design, selections and ordering were done. The three rooms shared one palette (natural wood, matte black fixtures and quiet stone-look tile), so design and selections were done once for the whole home. Across the project, QUAY added heated floors upstairs, built two new tiled showers, replaced two floor-mount toilets with wall-hung models and fitted custom vanities in all three rooms.

The master ensuite: about $67,000

The ensuite was a long room with a single white cabinet vanity, a wall of mirror and builder-grade tile. It was stripped back, and a new wall was framed behind the vanity so the plumbing could run inside it.

The finished room has:

  • a floating wood double vanity with a quartz countertop, two round vessel sinks and wall-mount black faucets;
  • mirrored medicine cabinets with LED lighting over a wood-lined open shelf;
  • a freestanding soaker tub with a black floor-mount filler under the window;
  • a tiled walk-in shower with a recessed niche, a rain head and a glass enclosure;
  • grey stone-look tile on the floor and walls, over NuHeat floor heating run by a smart thermostat;
  • a wall-hung toilet with a concealed in-wall tank, a heated towel rail, three new pot lights and a quiet fan;
  • a custom wood slat ceiling that ties the room to the trees outside.

Why it cost the most: almost every item our cost guide associates with large and luxury bathrooms is on that list: a double vanity, a freestanding tub, a large walk-in shower, custom millwork and heated floors, plus plumbing moved into a new wall. The guide puts large bathrooms (about 75 sq. ft. and up) at $40,000–$70,000+, and its Luxury / Bespoke level, which includes freestanding tubs, bespoke millwork and architectural detailing, at $65,000+. At about $67,000, this ensuite sits right where those two descriptions meet.

Freestanding soaker tub with a black floor-mount tub filler under a forest-view window in a North Vancouver ensuite

The main bathroom: about $39,000

The upstairs main bathroom is the one the kids use every day, so it had to be durable as well as good-looking. The bulkhead and popcorn ceiling came out, and the room was rebuilt around a new tiled shower in place of the old setup.

  • The shower has a linear drain, a recessed niche, a black rain head with a hand shower and a glass swing door.
  • Fluted, wood-look wall tile gives the shower texture; large dark porcelain tile covers the floor, over NuHeat floor heating with a smart thermostat.
  • A white oak vanity with drawers, a quartz top and an undermount sink sits under an oval mirror, with a vanity light in place of the old pot lights.
  • Textured wallpaper keeps the rest of the room soft and warm.

Why it landed in the middle: this is a full rebuild with a new shower and heated floor, but without a tub, a double vanity or millwork on the ceiling. Our cost guide’s Premium level ($32,000–$45,000+) describes it closely: an upgraded vanity, premium tile, better fixtures, heated flooring and moderate layout changes. At about $39,000, the main bathroom sits inside that range.

Tiled shower with fluted wall tile, recessed niche and black rain shower in a North Vancouver main bathroom

The powder room: about $22,000

The main-floor powder room had a pedestal sink, a dark paint colour and a bulkhead that made it feel smaller. It was taken back to the studs and rebuilt as a small room with a big feature wall:

  • a vertical wood slat wall, floor to ceiling, behind a wall-hung toilet with a concealed in-wall tank;
  • glossy green handmade-look tile on the lower walls, with sage green paint above;
  • a floating wood vanity with a quartz top, a vessel sink and a wall-mount black faucet, under an oval black-framed mirror and a relocated vanity light.

Why it cost the least: there is no shower and no tub, so there is no shower waterproofing or glass. It still needed demolition, framing and plumbing for the wall-hung toilet, tile, a custom vanity, millwork and electrical work. At about $22,000 it came in under the cost guide’s current planning range for small bathrooms ($25,000–$35,000+), whose common scope includes a tub or compact shower; the project was also completed in 2023. For what a powder room on its own involves, see our powder room renovation guide.

Powder room with a wood slat feature wall, green tile wainscot, vessel sink and oval mirror in North Vancouver

One project, three phases

The owners wanted all three bathrooms redone together, with a warmer, more modern look that matched the forest views outside. QUAY handled the design, finish selections and construction for all three, and each room was planned as its own phase: about two weeks of construction for the powder room, about two weeks for the main bathroom and about three weeks for the ensuite.

Renovating every bathroom in one project often saves time and money: you go through design and selections once, the trades are already on site, and the rooms can share one look. Planning each room as a phase keeps that advantage while giving each room its own clear scope and schedule. In any home with more than one bathroom, it also lets you ask for a schedule that keeps one bathroom working while another is under construction.

Two timing details matter when you plan several rooms:

  • Design and ordering come first. The construction times above start once planning, selections and ordering are complete. Many complete bathrooms need about ten working days on site at that point; larger ensuites and custom work take longer.
  • Glass has its own lead time. Custom glass shower enclosures usually take around three weeks to fabricate and are installed shortly after the tile is finished, so a project with two new showers plans around two glass orders.

Our guide to how long a bathroom renovation takes walks through each stage from design to handover.

What drives the cost of a townhouse bathroom

Our cost guide gives townhome bathrooms a common planning range of $25,000–$50,000+. Townhouses often allow more flexibility than condos, but they can still involve strata or shared-property requirements. Four things move a bathroom within that range, and all four show up in the Northlands project:

Cost driverWhat the cost guide saysHow it showed up in this townhouse
SizeLarger showers, double vanities and more tile add material and labourThe long ensuite carried a double vanity, a walk-in shower and a freestanding tub; the powder room had neither shower nor tub
Property typeCondos, townhomes and houses have different access, technical and approval requirementsA townhouse: more flexibility than a condo, but possible strata approvals (see below)
SpecificationTile, vanity construction, plumbing fixtures, glass, countertops and lighting can change the budget significantlyCustom wood vanities with quartz in all three rooms, wall-hung toilets in two, NuHeat floors in two, fluted and handmade-look tile
Existing conditionsOld plumbing, previous renovations, moisture and structural conditions can add workBulkheads and popcorn ceiling texture removed; a new wall framed to carry the ensuite plumbing

Two features in this project deserve a note because they are common requests on the North Shore:

  • Wall-hung toilets. They need a concealed in-wall tank, new framing and backing, and usually a drain relocation. They free up floor space and make the floor easier to clean, but they add plumbing and framing work compared with a like-for-like toilet swap.
  • Heated floors. NuHeat floor heating went under the tile in the ensuite and the main bathroom, each on its own smart thermostat, so the floors are warm in the morning without heating the whole house.

Square footage alone is a poor predictor. Waterproofing, fixture count, plumbing changes, tile complexity and glass often matter more than floor area, which is why a powder room and an ensuite in the same home can be $45,000 apart. To compare this project with others, see eight real QUAY bathroom budgets, from single condo bathrooms to this three-room townhouse, or read about our complete bathroom renovation services.

Permits and strata approval in North Vancouver

Which municipality? North Vancouver has two municipalities, each with its own permits: the City of North Vancouver (most of Lonsdale) and the District of North Vancouver (including Lynn Valley, Deep Cove and Northlands). Check which one your address is in before you plan the schedule.

Trade permits. The District’s Building Permit Guide (October 2025) says you must apply for permits if you are doing trades-related work such as electrical, drainage, gas, heating and plumbing as part of a project, including a plumbing permit if you are installing or altering plumbing-related fixtures and systems. In practice, work that moves walls, plumbing, gas or electrical usually needs permits. QUAY handles the applications for your address. For a North Shore bathroom that needed a full building permit as well, see our West Vancouver ensuite addition, which came in at about $58,000 + GST including design and permits.

Strata approval. Many townhouses are strata-titled, and then the strata’s bylaws apply as well as the municipality’s permits. Under the Standard Bylaws of the Strata Property Act, an owner must get the strata corporation’s written approval before altering a strata lot where the work involves the structure of the building, common property inside the strata lot, or the parts of the lot the strata corporation must insure; the strata must not unreasonably withhold approval, but it can require you to agree in writing to take responsibility for related expenses. The Province notes that a strata’s bylaws are the Standard Bylaws unless different bylaws are filed, and that many bylaws require written permission before plumbing or electrical changes, often through an alteration agreement. Read your strata’s filed bylaws and get any approval in writing before demolition starts.

Floating wood vanity and wall-hung toilet in front of a wood slat wall in a North Vancouver powder room

Planning several bathrooms at once: a checklist

  1. Give each room its own scope and budget. Use the table above as a starting point: an ensuite with a tub and shower, a main bathroom with a shower, and a powder room are three different budgets, not one number split three ways.
  2. Make selections for all rooms in one design phase. One palette across the house keeps decisions faster and the rooms consistent.
  3. Decide where plumbing moves. Wall-hung toilets, floating vanities with wall-mount faucets and new showers usually mean drains or supply lines move, which affects cost and permits.
  4. Confirm the municipality, permits and any strata approval before demolition, as above.
  5. Order long-lead items early, especially custom shower glass (about three weeks to fabricate).
  6. Sequence the rooms so the schedule works for the people living in the home, with the longest room (usually the ensuite) planned in its own phase.

North Vancouver townhouse bathroom FAQ

How much does it cost to renovate three bathrooms in a North Vancouver townhouse?

In QUAY’s Northlands townhouse project, three bathrooms came in at about $128,000 together in 2023: about $67,000 for the master ensuite, about $39,000 for the main bathroom and about $22,000 for the powder room. Cost depends mostly on size, whether plumbing moves, and finishes such as heated floors, wall-hung toilets and custom vanities.

Is it cheaper to renovate all your bathrooms at once?

It often saves time and money. You go through design and selections once, the trades are already on site, and the rooms can share one look. On the Northlands project each bathroom was still planned as its own phase.

How long does it take to renovate three bathrooms?

On the Northlands project, construction took about two weeks each for the powder room and the main bathroom and about three weeks for the ensuite, after design, selections and ordering were complete. Custom glass shower enclosures usually take around three weeks to fabricate.

Do you need a permit to renovate a bathroom in the District of North Vancouver?

The District’s Building Permit Guide says trades-related work such as plumbing, electrical, drainage, gas and heating needs permits, including a plumbing permit when you install or alter plumbing fixtures and systems. Work that moves walls, plumbing, gas or electrical usually needs permits. The City of North Vancouver issues its own permits for addresses in the City.

Do you need strata approval to renovate a townhouse bathroom?

If the townhouse is strata-titled, often yes. Under the Strata Property Act’s Standard Bylaws, an owner needs the strata corporation’s written approval before altering the structure, common property inside the strata lot, or parts the strata must insure, and many stratas’ own bylaws require written permission for plumbing or electrical changes. Check your strata’s filed bylaws.

Why did the powder room cost so much less than the ensuite?

The powder room has no shower or tub, so it needed no shower waterproofing or glass. The ensuite had a double vanity, a freestanding tub, a walk-in shower, heated floors, a wood slat ceiling and plumbing moved into a new wall, which is why it came in at about $67,000 against about $22,000 for the powder room.