QUAY Construction

Completed retail store with slat wall, quartz countertops and track lighting before merchandise was installed

Sign Permit in Vancouver: What Retailers Need Before Opening

The short answer

In Vancouver, almost every sign on private property needs its own sign permit: fascia signs, projecting signs, awning and canopy signs, freestanding signs and street-level awnings on commercial buildings. Window signs, banners and signs showing only the building number and street name don’t. Under the City’s Sign Fee By-law the standard application fee is $384 per sign, including one inspection, and a lit sign adds a $195 electrical connection fee. Apply as soon as the sign design is final so the permit runs alongside the eight to twelve weeks of construction most store build-outs take.

This guide walks through the City of Vancouver’s sign rules from a contractor’s side of the job: which signs need a permit, the numbers in the Sign By-law that most often shape a storefront, what goes into the application, and how to keep the sign from becoming the last thing holding up your opening. If you are planning the whole store, our retail renovation service in Vancouver covers design, permits and construction under one contract.

Everything below comes from the City’s own pages and by-laws, linked where they are used. The Sign By-law always takes precedence over the City’s user guides, and the City updates its fees, so check the linked pages before you budget or submit.

Which signs need a permit, and which don't

The City of Vancouver’s sign permit page is short and clear: a permit is needed for all signs on private property, and each sign needs its own permit. Two signs on one storefront, a fascia sign and a projecting blade sign for example, are two applications and two fees.

Awnings follow their own rule. According to the City’s awning permit page, an awning on the outside of a commercial or industrial building at or below the first floor needs a sign permit. An awning above the first floor, or on any other kind of building, needs a development permit and/or a building permit instead.

Sign type (private property)Sign permit needed?
First-storey fascia sign (the main sign over the door)Yes
Second-storey or upper-level fascia signYes
Projecting (blade) signYes, plus a building permit
Awning sign, under-awning sign, canopy and under-canopy signYes
Street-level awning on a commercial buildingYes (sign permit)
Freestanding signYes, plus a building permit
Window signNo
Banner sign (flexible, unlit, perpendicular to the building)No
Building number and street name onlyNo
Sign inside the store that can't be seen from the streetNo sign permit; may need a building permit, and an electrical permit if lit

Sources: City of Vancouver sign permit page and Sign By-law user guide for business identification signs.

Step 1: Find your sign district

What you can put on a storefront depends on where the store is. The City’s Sign By-law framework page and the business identification guide divide private property into seven sign districts:

  • Commercial, Mixed-Use and Industrial (Part 9), which covers most high streets and retail units.
  • Residential (Part 8).
  • Five special districts: Chinatown and Gastown Historic (Part 10), West End (Part 11), Granville Street (Part 12), Rogers Arena (Part 13) and International Village (Part 14).

To find yours, look up the property’s zoning on the City’s VanMap and match it to a sign district (Part 7 of the by-law does this for standard zones). Sites zoned CD-1 are assigned by Schedule A or B of the by-law; a CD-1 zone on neither schedule falls under the Residential sign district. The district goes on the application form, so settle it before your sign company starts drawing.

If the building is on the Vancouver Heritage Register, the City’s application form says you also need a Heritage Alteration Permit. In Gastown and Chinatown, the historic district rules in Part 10 apply instead of the standard commercial ones.

The size and placement rules storefronts run into

The numbers below are from the City’s business identification guide for the Commercial, Mixed-Use and Industrial district (Part 9). They are the limits that most often shape a typical street-level store. Other districts have different numbers, and the by-law itself governs if anything differs.

  • First-storey fascia signs: copy area of 0.6 m² for each metre of frontage, with a maximum vertical dimension of 0.6 m. A store with 6 m of frontage gets up to 3.6 m² of copy area on its first-storey fascia.
  • Projecting signs: one per premises at the first storey. The allowed sign area runs from 0.075 m² to 0.30 m² per metre of frontage, depending on zoning.
  • Awning signs: at least 2.75 m of clearance above grade and no higher than 6 m. Under-awning signs also need 2.75 m of clearance and can be at most 0.3 m tall and 1.5 m long.
  • Canopy signs: copy area of 0.6 m² per metre of frontage; under-canopy signs at most 0.45 m tall and 1.5 m long.
  • Window signs: no permit, but they can cover no more than 30% of the contiguous first-storey glass, and they generally can’t be lit.

Lighting. Most signs on private property may be illuminated. The guide says illumination must not exceed 3.0 lux above ambient light on an adjacent site or street, externally lit signs need a shield, and signs shouldn’t be lit from below. Signs near homes can have extra limits on hours.

In practice, frontage is the number to measure first. It sets the copy area for fascia and canopy signs, and it is the question a sign company will ask before it can tell you how big your logo can be.

Wood slat wall and cash desk millwork being installed during construction
Millwork going in at Top Drawers Apparel on Hornby Street. Power and backing for signs are best placed at this stage, before finishes close the walls.

How to apply for a sign permit, step by step

The City’s guide and sign permit application form set out the process. The sign drawings usually come from your sign company, and the owner, tenant, sign company or another agent can be the applicant.

  1. Confirm the sign needs a permit and which sign district applies.
  2. Get landlord approval of the design. The City needs an owner’s undertaking letter signed by the property owner or an authorized signatory, on the City’s form, and shopping centres usually have their own sign criteria on top of the by-law.
  3. Prepare the drawings. Two scaled sets with metric dimensions: the sign copy with its wording, height, width, depth, sign area and copy area; a site plan with property lines and the distance from the sign to the nearest property line; an elevation showing the clearance from grade to the bottom of the sign; and, for signs mounted on the building, a partial section showing the projection from the face. Add a current photo of the premises with no digital additions.
  4. Add supporting permits and documents where they apply. A building permit for signs over 200 lb, freestanding signs, projecting signs and signs above the second storey. Structural drawings for signs over 200 lb, freestanding signs and signs above the second storey (two signed and sealed sets, a signed and sealed Schedule B Letter of Assurance and a Structural Concept Review Letter). An electrical permit for a lit sign’s permanent power connection, taken out by a licensed electrical contractor. An awning permit for a new awning structure. A Heritage Alteration Permit for a heritage property.
  5. Fill in one form per sign with the sign contractor, owner and tenant details, and submit online through the City’s application portal or in person at the Development and Building Services Centre, 515 West 10th Avenue. The form warns that incomplete applications can’t be processed and are returned.
  6. Pay the application fee when you submit.
  7. Call 3-1-1 for an inspection once the permit is issued and installation begins.

Fees: what the City charges

Fees are set by the Sign Fee By-law. The consolidated version on the City’s by-law site lists these:

ItemFee
Sign permit, per sign (excluding billboards), includes one field inspection$384
Sign reviewed by the Director of Planning under Part 15 (a relaxation), includes one inspection$908
Electrical connection, includes one electrical inspection$195
Each additional inspection$222
Revisions to a sign permit$59 per hour of staff review
Sign put up without a permitDouble the permit fee

Source: City of Vancouver Sign Fee By-law No. 11880, consolidated version, read November 2026. Fees change; confirm the current schedule before you submit.

For a typical store with one lit fascia sign and one lit blade sign, that is two permit fees and two electrical connection fees, plus the separate building permit the projecting sign needs. These are City fees only: the sign itself, its installation and the electrical work are quoted by your sign company and electrician, and the backing and power in the wall are part of the build-out.

The double fee for a sign put up without a permit is worth noting. If an installer offers to hang the sign before the permit comes through so you can open on time, the shortcut can cost more than the wait.

When the sign doesn't fit: relaxations and timelines

If the sign you want is bigger, higher or in a different spot than the by-law allows, you can ask for a relaxation under Part 15. According to the City’s relaxations guide, a relaxation can cover height, sign area, copy area, vertical dimension, location, the number of signs on a site or sign width. The Director of Planning decides case by case after a technical review, looking at whether the sign fits the character of the area and how it affects neighbours. The accepted reasons are unique site circumstances that cause unnecessary hardship, heritage properties or historic areas, historic signs, signs for a Council-designated special event, and new technology the by-law doesn’t contemplate.

You apply with the normal sign permit application plus a rationale letter explaining why the relaxation is needed, which rules you want relaxed and why a compliant sign won’t work. The guide says the process may take approximately 4 to 8 weeks after a complete application, and an appeal to City Council about 6 months, with a written request to the City Clerk within 14 days of the decision.

The City doesn’t publish a standard processing time for an ordinary sign permit. For an opening date, the safer plan is to design a sign that complies, submit it early, and keep a relaxation only for when the storefront genuinely can’t take a compliant sign.

Fitting the sign into your store build-out

The sign is permitted separately from the construction, and that is exactly why it gets left too late. Most retail store renovations take about eight to twelve weeks of construction once permits are in place and materials are ordered, and the sign should be designed, approved by the landlord and submitted inside that window, not after it.

On our projects, the split is usually this: QUAY builds the storefront, power and backing the signs need and coordinates the sign permit alongside the building and electrical permits, your sign company makes and installs the sign, and your landlord approves both. A few things make that run smoothly:

  • Fix the sign location and size during design, once you know the frontage and sign district, so the electrician can bring power to the right spot and the framer can add solid backing before the walls are finished.
  • Submit the sign permit while construction is underway, not when the store is nearly done. The sign company can’t install until the permit is issued.
  • Plan storefront changes with the sign. New glazing, entrances and storefront systems need landlord approval and often a building permit, and storefront glazing is one of the longest lead items in a store build-out.
  • Keep the sign out of the critical path. If the sign can’t be ready, a compliant window sign needs no permit and can carry the name for the first weeks.

For a sense of pace on a small store: QUAY built the Top Drawers Apparel menswear store on Hornby Street downtown, about 750 sq ft, in about a month in October 2022, for a $75K–$100K + GST contract. The millwork was fabricated while site work started. On a job that fast, a sign permit applied for at the end would easily be the last thing outstanding.

The City’s Small Business Commercial Renovation Centre can also help you understand the permits a location will need before you sign a lease. Our guide to commercial permits explains the building and trade permits that run alongside the sign permit.

Cash desk clad in wood slats with a white quartz countertop in front of the slat feature wall
The finished Top Drawers Apparel cash desk and slat wall, built in about a month in 2022.

Sandwich boards, hoarding and window signs

Sandwich boards (A-boards) on the sidewalk aren’t covered by the Sign By-law, which applies to private property. They fall under the Street and Traffic By-law, and Engineering Services’ sandwich board guidelines allow them if you follow the rules: one sign per street-level storefront, a suggested maximum of 90 cm by 60 cm, placed directly against the building (not at the curb, on the boulevard or in the middle of the sidewalk), and only advertising the business’s own products and services. After a warning, City staff can remove a sign, with an impoundment charge of at least $100.

Hoarding signs on a construction fence or covered walkway are handy for a “coming soon” message while you build. The City’s hoarding sign guide says large hoarding signs need a permit and that hoarding signs must not be lit.

Window signs need no permit but must stay within 30% of the contiguous first-storey glass, and they generally can’t be lit, apart from one small electronic message sign of no more than 0.34 m² of copy area.

Sign permit checklist

  • Measure the store’s frontage and confirm the zoning and sign district.
  • Get the landlord’s or shopping centre’s sign criteria before design starts.
  • Decide the sign types: fascia, blade, awning, window. Each permitted sign is a separate application.
  • Set sign locations during store design so power and backing are built in.
  • Have the sign company prepare two scaled metric drawing sets and a current photo of the storefront.
  • Get the owner’s undertaking letter signed.
  • Add a building permit and sealed structural drawings where the sign needs them, an electrical permit for lit signs, and a Heritage Alteration Permit for heritage buildings.
  • Submit while construction is underway, and pay the fee per sign.
  • Call 3-1-1 for the inspection once installation begins.

Sign permits in Vancouver: FAQ

Do I need a permit for a store sign in Vancouver?

Usually, yes. The City of Vancouver requires a permit for all signs on private property, and each sign needs its own permit. Window signs, banners, signs showing only the building number and street name, and interior signs that can't be seen from the street don't need a sign permit.

How much does a sign permit cost in Vancouver?

The consolidated Sign Fee By-law lists $384 per sign, including one inspection, plus $195 for an electrical connection on a lit sign. A sign reviewed under Part 15 for a relaxation is $908. Fees change, so check the current by-law before you submit.

Does an awning need a sign permit?

An awning on the outside of a commercial or industrial building at or below the first floor needs a sign permit. Above the first floor, or on other buildings such as homes, it needs a development permit and/or a building permit instead.

Who applies for the sign permit, the sign company or the contractor?

The applicant can be the sign company, the owner, the tenant or another agent. The sign drawings usually come from the sign company, and on QUAY projects we coordinate the sign permit with the building and electrical permits. The property owner signs an undertaking letter, and a lit sign needs a licensed electrical contractor for the power connection.

How long does a sign permit take in Vancouver?

The City doesn't publish a standard processing time for ordinary sign permits. Its relaxations guide says a relaxation may take approximately 4 to 8 weeks after a complete application, so submit early and design a compliant sign where you can.

Do I need a permit for a sandwich board on the sidewalk?

Sandwich boards on the sidewalk fall under Engineering Services' guidelines rather than the Sign By-law. One board per street-level storefront is allowed, with a suggested maximum of 90 cm by 60 cm, placed directly against the building.

Ready to get started?

Tell us about the unit, the opening date and the storefront you have in mind, and we'll plan the build-out, the power and backing for your signs and the permits around it.

Book a discovery call

See our retail renovation services