Tenant Improvement Permits in Burnaby, Richmond and Surrey: What Each City Asks For

Short answer: Burnaby, Richmond and Surrey all require a building permit for a tenant improvement that changes walls, plumbing, electrical or mechanical systems, the exterior or the use of a commercial unit. The permit itself is similar in all three; what differs is the paperwork around it. Burnaby may need Preliminary Plan Approval from its Planning Department before it will issue the permit, Richmond ties the permit to your business licence and an Environmental Health review, and Surrey asks for a Zoning Approval Letter and its own Tenant and Landlord Improvement Checklist.

For budgeting, QUAY’s published planning ranges for build-outs run from about $90 to $400+ per square foot depending on the use, and our tenant improvement permit and build-out service covers the applications in each of these cities. One recent Burnaby example, an office and warehouse for Five Star Building Services, came in at $175K to $250K + GST with about eight weeks of construction.

This guide compares what each city asks for, using only the cities’ own permit pages and bulletins (linked in every section) as they read in November 2026. Requirements change, so open the linked page before you apply. If your unit is in Vancouver, the rules are different again: read our guide to Vancouver TI permits and the TIPs program.

Burnaby, Richmond and Surrey at a glance

 BurnabyRichmondSurrey
How you applyBuilding Division counter with 3 complete sets of drawings (City TI guide)One email to the City's building applications inbox, or hard copy at City Hall in triplicateBy email following the digital submission guide, or in person with 4 printed sets per discipline
Core formsTI application form, Schedule "F" owner's undertaking, Agent Authorization, Consent to Construction where requiredApplication form, Letter of Authorization from all owners, proof of strata approval if stratifiedBuilding Permit Application Form, Tenant and Landlord Improvement Checklist, Owner Authorization Form
Planning or zoning stepPreliminary Plan Approval (PPA) for changes of use, added floor area, mezzanines, exterior changes and moreBusiness licence application confirms the use complies with the Zoning BylawZoning Approval Letter from Business Licensing, requested with a Bylaw Inquiry Form
Health approvalFraser Health approval before you apply, for food, personal services, pools and hot tubs, and childcareEnvironmental Health approval for food, personal services, schools and daycares; the City circulates your applicationFraser Health approval before the permit is issued; two sets of plans signed by a Fraser Health inspector
Quicker streamFast track for simple TIs in buildings in substantial compliance with the Building CodeNone described on the City's TI pagesMinor Tenant Improvement permit for small, low-complexity interior work
Contractor licenceValid Burnaby or Inter-Municipal Business LicenceGeneral contractor's Richmond or Metro-West Inter-Municipal Business Licence numberNot covered on the City's TI page
Official sourceBurnaby commercial renovationsRichmond commercial and industrialSurrey tenant and landlord improvement

The pattern is the same everywhere: confirm the use is allowed, clear any health or planning review, submit complete drawings and forms, then pull separate trade permits once the building permit is issued. The order of those steps, and which department you talk to first, is where projects lose weeks.

Burnaby warehouse before pallet racking install, with layout dimensions marked on the walls
Racking is on Burnaby's list of work that needs a TI permit. Here the layout for the Five Star warehouse in South Burnaby was marked out on site before installation.

Burnaby: fast track, full review and Preliminary Plan Approval

Burnaby’s commercial renovations page says any interior or exterior alteration or change of use to an existing commercial, industrial or multi-residential building, tenant improvements included, needs a building permit. The City’s Tenant Improvement Permits informational guide lists examples: alterations to the interior layout or the exterior, adding a mezzanine or storey, increasing floor area, installing or modifying a commercial kitchen exhaust system, repiping, racking, spray booths, fire alarm alterations and changing the use of a business.

Two review tracks

A plan checker decides whether your application is simple enough to fast track. Only straightforward applications in buildings that are in substantial compliance with the BC Building Code qualify. The guide lists what does not qualify, including:

  • schools, restaurants, social clubs, night clubs and similar assembly occupancies;
  • a change of major occupancy or a building reclassification;
  • most exterior alterations, and floor area additions such as mezzanines;
  • upgrades to exits, fire alarms, sprinklers or seismic systems;
  • structural or complex changes that need letters of assurance from registered professionals;
  • anything that needs Fraser Health, Engineering or Fire Department approval, or an alternative solution.

Everything else goes through full plan review, where drawings are circulated to Fire, Electrical, Plumbing and Gas, and Engineering as needed. The guide says processing time depends on the complexity of the project; it doesn’t publish a fixed timeline.

Preliminary Plan Approval comes first

Some projects need Preliminary Plan Approval (PPA) from the Planning Department before a building permit can be issued. The guide’s examples include changing the use of a business (office to school, say), increasing the office area in a former warehouse space, adding seats to a restaurant, exterior changes, mezzanines, added floor area and a higher occupant load. The City says to confirm PPA requirements with Planning before signing a lease, and that the building permit must be applied for within 90 days of PPA approval.

Forms, health approval and trades

Burnaby’s TI permit application form (revised August 2026) asks for the project value, occupancy type and a Planning section that Planning staff must complete. With it go a Schedule “F” owner’s undertaking, an Agent Authorization form if someone applies for you, and where required a Consent to Construction signed by the strata or property manager. Food service, personal service (salons, esthetics, tattoo, massage and similar), recreational water and childcare uses need Fraser Health approval before you apply, with the approval memo and one set of stamped plans in the package. Electrical, plumbing, gas and sprinkler permits are separate and are pulled by certified trade contractors after the building permit is issued.

Richmond: business licence, Environmental Health and one complete package

Richmond’s Tenant Improvement Process bulletin (INFO-13, revised August 2025) sets out three approvals that run side by side:

  1. Business licence. It confirms the proposed use complies with the Zoning Bylaw and the Business Licence Bylaw. You apply online through MyBusiness or with the fillable form.
  2. Environmental Health. Food premises, personal service facilities (barbers, salons, tanning, tattoo, massage therapy, fitness clubs and similar) and schools and daycares need its approval. Building Approvals circulates your building permit application to Health, so it isn’t a separate submission.
  3. Building Approvals. The building permit covers life safety, structure and health under the BC Building Code, and a plumbing permit is needed whenever fixtures are removed or added.

The City’s commercial and industrial “know before you apply” page says incomplete applications aren’t accepted and lists what goes in the package: a Letter of Authorization signed by all property owners (not needed if the applicant is the sole owner), proof of strata approval for a stratified property, Schedules A, B, E and F where registered professionals are involved, a hazardous materials declaration for pre-1990 buildings, a food cooking occupancies form where it applies, and a traffic and parking plan during construction. A damage deposit form is due before issuance. The general contractor’s Richmond business licence or Metro-West Inter-Municipal Business Licence number is also required.

When we checked in November 2026, that page said online applications for these permits were not yet open on MyPermit, so applications go to City Hall or in one email to the City’s building applications address. The page also recommends retaining an architect or building code consultant to review the existing building, because a change in occupancy can trigger upgrades that are “cost prohibitive or impractical” in an existing building.

Small details that catch people out

The bulletin says sprinkler work may need plans if five or more new heads are added or 13 or more are relocated, and that a commercial exhaust hood and fire suppression system, structural changes such as a mezzanine or new openings in a structural wall, and major changes to the heating and ventilating layout may need a registered professional with letters of assurance. Richmond’s commercial building permit requirements page adds that permit fees rise every January 1 under the consolidated fees bylaw.

Surrey: the Tenant and Landlord Improvement permit

Surrey calls it the Tenant and Landlord Improvement Building Permit, and it is the clearest of the three about where the line sits. A permit is required for any new construction or alteration within a building, including installing, relocating or building doors, walls, stairs, shelving or racking, equipment, washroom fixtures, spray booths, commercial cooking equipment, dust collection systems and caretaker suites. The City says a permit is not required for replacing flooring, interior painting or minor repairs that don’t involve material changes.

For small, low-complexity interior work there is a Minor Tenant Improvement permit, reviewed quickly once a building official confirms eligibility. Surrey’s examples include warehouse racking, restoration work with no layout changes, minor layout updates in offices and small business improvements with no exterior changes.

What goes in the package

  • the Building Permit Application Form and the updated Tenant and Landlord Improvement Checklist;
  • an Owner Authorization Form if you are not the owner, and a strata letter if the work is in a strata unit and affects common property;
  • Schedules A and B from registered professionals, with proof of liability insurance for each one who provides a Schedule B;
  • parking calculations if they apply;
  • a Zoning Approval Letter, which Business Licensing issues after you submit a Bylaw Inquiry Form;
  • for food, personal services and recreational uses, two sets of plans reviewed and signed by a Fraser Health inspector before the permit is issued.

Applications go in by email or in person on the second floor of City Hall; paper submissions need four printed sets of drawings per discipline with original wet seals. A non-refundable flat fee based on the cost of work is collected at review, and the balance is due before issuance.

Referrals that add review time

Surrey’s page lists which projects get referred: plumbing for new or relocated fixtures; electrical for panel upgrades and patient care areas; Fire Department review for assembly uses over 60 people and changes to life safety systems; Engineering review for projects over $250,000 in construction value; and district energy review for projects in the catchment over $120,000. If you are combining strata units without demising walls, the plan reviewer decides whether a land surveyor’s posting plan or a restrictive covenant is needed. The City’s commercial building permits page also notes City Hall is closed from December 25, 2026 to January 4, 2027, so plan holiday-season submissions around it.

The drawings all three cities expect

The three cities word it differently, but a complete TI drawing set looks much the same in each. Their pages and guides ask for:

  • A site or key plan showing the building on the lot, the tenant unit’s location and suite number, and the uses of neighbouring units.
  • A dimensioned floor plan of the whole space, with room uses, new and existing walls shown differently, door sizes, exits, travel distances, exit signs, emergency lighting and plumbing fixtures. For restaurants and other assembly uses, the seating layout and occupant load.
  • Sections and construction details showing wall, floor and ceiling assemblies and the fire-resistance rating of separations between tenants.
  • Elevations only if the exterior changes.
  • Trade drawings where the work calls for them: electrical (load calculations and a single-line diagram), plumbing (Richmond asks for drain, vent and water piping sized to the BC Plumbing Code; Surrey asks for isometrics with the plumbing contractor’s name), mechanical, sprinkler and structural.

Burnaby asks for double-line drawings on sheets between 11 x 17 and 24 x 36 inches, Surrey specifies scales (floor plans at 1/4″ = 1′-0″), and Richmond asks that drawings distinguish new from existing construction and be legible enough to scan. All three warn that unclear or incomplete drawings slow the application or get it rejected.

When you need an architect or engineer

A simple office or retail refit can often be drawn by a designer. These items, taken from the three cities’ pages, usually bring in a registered professional who seals drawings and provides a Schedule B:

  • Architect: Surrey lists assembly occupancies, construction upgrades, fire separation changes, new universal washrooms, accessible service counters, mezzanines and power door operators.
  • Structural engineer: mezzanines and added floors, new openings in structural walls, racking systems, exterior changes and (in Surrey) new walls over 12 feet high.
  • Mechanical engineer: commercial cooking exhaust and fire suppression, spray booths and dust collection.
  • Electrical engineer: Surrey requires one for food service, patient care areas such as medical and dental clinics, labs, electrical service upgrades, EV charging and hazardous locations.
  • Fire sprinkler designer: any new or altered sprinkler system. Surrey reviews the sprinkler drawings with the building permit.

When more than one registered professional is involved, all three cities expect a coordinating professional’s Schedule A. That is a cost and a lead time to build into your schedule before the lease start date, not after.

Change of use: the trigger that costs the most

The most expensive surprise in a TI is rarely the finishes. It is moving a unit into a use the building wasn’t designed for. Richmond’s bulletin gives the textbook example: a building designed for industrial use (F2 occupancy) leased to an assembly use (A2), such as a gym, church or restaurant. The original building may not meet the stricter construction and fire safety requirements of the new use, and the code analysis can call for major changes to the whole building, not just your unit.

Burnaby handles the same risk through Preliminary Plan Approval and by excluding changes of major occupancy from its fast track. Surrey refers assembly uses over 60 people to the Fire Department and assembly uses to Planning. In every city, the question to answer before you sign is simple: is my use allowed here, and what does the building need for it? Our pre-lease walkthrough guide covers the physical checks that go with it.

Main meeting room after renovation with fresh paint and new carpet in a Burnaby office
The renovated meeting room at the Five Star Building Services office in South Burnaby.

Before you sign the lease: a checklist

  1. Confirm the use. Burnaby: ask Planning whether you need PPA. Richmond: check the zone’s permitted uses and apply for your business licence. Surrey: send a Bylaw Inquiry Form for a Zoning Approval Letter.
  2. Check for health review. Food, personal services, childcare and similar uses need Fraser Health (Burnaby, Surrey) or Environmental Health (Richmond) approval of your plans.
  3. Get the owner’s paperwork lined up. Schedule “F” and Consent to Construction (Burnaby), a Letter of Authorization (Richmond), an Owner Authorization Form (Surrey), plus strata approval if the unit is stratified.
  4. Ask the landlord for the base building drawings and the existing occupancy, so your designer can check exits, washrooms and fire separations.
  5. List the professionals you’ll need from the section above, and get their fees and lead times.
  6. Build permit time into the lease. None of the three cities publishes a fixed review time for TIs, so negotiate a fixturing period or rent start date that allows for it.
  7. Get a fixed-price construction budget before you commit, with the permit and professional costs shown separately.

For the full sequence from lease to opening day, see the tenant improvement process, step by step.

How QUAY handles TI permits outside Vancouver

QUAY is a design-build contractor based at 928 Homer Street in Vancouver, and we build tenant improvements across Metro Vancouver, including commercial renovations in Burnaby, Richmond and Surrey. We review the unit, the lease and how your operation runs before pricing, and where a mezzanine, a new washroom or a change of use calls for structural engineering or a building permit, we coordinate the engineer and the application with the city your unit is in. You get a detailed fixed-price proposal that lists the scope, inclusions, exclusions and allowances before anything is built.

For a sense of scale, the Five Star Building Services office and warehouse in South Burnaby included two new staff kitchens, about 2,500 sq ft of new carpet, about 4,200 sq ft of painting, a refreshed T-bar ceiling and steel pallet racking with 50 wire mesh decks. It was built in about eight weeks in summer 2025, for $175K to $250K + GST including approved change orders. Our published planning ranges for other uses are on the tenant improvements page: about $150 to $250 per sq ft for a full office build-out, $100 to $220 for retail and $180 to $300 for a medical clinic. For warehouse units specifically, see our guide to warehouse office build-outs.

TI permits in Burnaby, Richmond and Surrey: FAQ

Do I need a permit for a tenant improvement in Burnaby?

Yes, for any interior or exterior alteration or change of use to an existing commercial, industrial or multi-residential building. Simple applications in code-compliant buildings may be fast tracked; others go through full plan review, and some need Preliminary Plan Approval first.

Can I apply for a Richmond tenant improvement permit online?

When we checked in November 2026, Richmond’s page said these applications were not yet available on MyPermit. Submit the complete package at City Hall or in one email to the City’s building applications address.

What work doesn’t need a permit in Surrey?

Surrey says replacing flooring, interior painting and minor repairs that don’t involve material changes don’t need a permit. New or relocated walls, doors, racking, washroom fixtures and commercial cooking equipment do.

When do I need health authority approval?

For food, personal service and similar uses. Burnaby wants Fraser Health approval before you apply, Surrey before the permit is issued, and Richmond circulates your application to Environmental Health itself.

How long does a TI permit take in these cities?

None of the three publishes a fixed timeline for tenant improvements. Burnaby says processing time depends on complexity, and Surrey says it depends on how complete the application is, how quickly you answer comments and review volumes. Complete applications and early health and zoning approvals are what keep it short.