New Westminster Renovation Permits: Houses, Heritage Homes and Strata Condos
By QUAY Construction · November 24, 2026 · Renovations
In New Westminster, renovating or adding on to a house or duplex needs a City building permit, and so does work inside a condo or townhouse that moves walls, disturbs a fire separation or replaces a bathtub or shower (that last one also needs a plumbing permit). New or moved plumbing needs a City plumbing permit, but swapping CSA-approved fixtures in place does not. Electrical and gas permits come from Technical Safety BC, not the City. In Queen’s Park, a Protected house also needs a Heritage Alteration Permit for changes visible from the street.
This guide goes through the City of New Westminster’s own permit pages project by project, with each source linked, so you can see what your renovation will need before you design it. If you are planning a larger project, our home renovation service covers design, permits and construction under one fixed-price proposal, and our renovation team in New Westminster coordinates the City and strata approvals during planning.
One rule of thumb runs through all of it, and the City says it directly on its plumbing permits page: if you are unsure whether a permit is required, contact the Building Division (604-527-4580) before starting work.
Which renovations need a permit in New Westminster: project by project
| Project | What New Westminster asks for | Source |
|---|---|---|
| Replace sinks, toilets or taps in the same place (CSA-approved fixtures) | No plumbing permit | City plumbing permits page |
| Move or add plumbing fixtures, or alter or extend the plumbing system (moving a kitchen sink, adding a bathroom) | Plumbing permit; a building permit must be issued first unless the work is plumbing only | City plumbing permits page |
| Renovate, or add on to, a house, duplex, laneway or carriage house | Building permit | City residential building permits page |
| Replace a bathtub or shower in a condo, apartment or townhouse | Building permit and plumbing permit | City multi-family renovation permits page |
| Move, remove or alter wood-framed interior walls in a condo or townhouse | Building permit, plus a structural engineer’s report certifying the walls are not structural | City multi-family renovation permits page |
| Any work that disrupts a fire separation in a multi-family building | Building permit | City multi-family renovation permits page |
| Building envelope or membrane repairs, cladding, exterior doors and windows on a multi-family building | Building permit, with a building envelope consultant involved | City multi-family renovation permits page |
| New garage, carport, shed or workshop over 10 square metres | Building permit | City residential building permits page |
| Add a secondary suite, or authorize an existing one | Zoning check with Planning, then a building permit and a tree permit | City secondary suite permits page |
| New or altered hydronic (hot-water) heating | Hydronic heating permit | City plumbing permits page |
| New or replaced water service, sanitary sewer or drain tile | Services permit | City plumbing permits page |
| New or changed electrical wiring, or gas lines and gas appliances | Any required permit comes from Technical Safety BC, not the City | Technical Safety BC jurisdiction page |
| Exterior changes visible from the street on a Protected house in Queen’s Park | Heritage Alteration Permit first, then any building permit | City Queen’s Park Heritage Conservation Area page |
The table is a summary, not a substitute for the City’s pages. Two things it cannot show: the City notes that additional documents may be required depending on the scope of work, and a single kitchen or bathroom often triggers several rows at once. Moving a condo kitchen sink to a new island, for example, means a plumbing permit, and if a wall comes out to make room, a building permit and an engineer’s letter as well. The same question for other cities is covered in our guides to permits in the City of Vancouver and renovation permits in Burnaby; the rules differ more than most people expect.
Who issues each permit: the City or Technical Safety BC
Two authorities issue renovation permits in New Westminster, and it matters which one you apply to.
- The City of New Westminster issues building permits through its Building Division, and plumbing, hydronic heating, services (water, sewer, drain tile) and fire sprinkler permits through its Building and Plumbing Division. These are set out on the City’s residential building permits, multi-family renovation permits and plumbing permits pages.
- Technical Safety BC issues electrical and gas permits. It administers the Safety Standards Act across the province, and only 10 local governments are delegated to issue their own electrical or gas permits. Burnaby, the City of Vancouver and both North Vancouvers are on that list; New Westminster is not, according to Technical Safety BC’s jurisdiction page. So any permit for electrical or gas work in a New Westminster renovation, such as new kitchen circuits or a relocated gas range, comes from Technical Safety BC rather than City Hall.
For plumbing, the City also spells out who can apply. A contractor needs proof of plumbing trade qualification and a current City of New Westminster business licence. A homeowner doing their own plumbing must show proof of ownership and sign a declaration taking responsibility for the work. Either way, the City says plumbing review takes a minimum of 48 hours after a complete application, longer with high volume, complex projects or inaccurate applications.
Houses and duplexes: applying and booking inspections
The City’s residential building permits page is blunt: if you plan to renovate, add onto or build a dwelling, such as a house, laneway house, carriage house or duplex, you need permits. Alterations and small projects can be applied for by email or online through a MyCity account. The online application asks for:
- a current title search (within 30 days);
- a letter of authorization, if someone applies on the owner’s behalf;
- a company summary or solicitor’s letter, if a company owns the property;
- consent of strata, if applicable (for example, a strata duplex);
- project drawings and other documents based on the scope.
A non-refundable application fee is paid by credit card when you submit, and the portal will prompt you for any precursor approvals the project needs, such as a tree permit, a Development Permit or a Heritage Alteration Permit. Files go in as PDF, Word or JPEG, up to 10 MB each, and the City will not accept links to cloud folders on emailed applications.
Once the permit is issued, the owner or their agent books each inspection through the MyCity Portal by 2:00 p.m. on the business day before, and work cannot proceed past a required inspection stage without the Building Division’s authorization. The City’s inspections page also says no one may occupy a building until an accepted final inspection. For plumbing, the required inspections run from rough-in under and above the slab, through the bathtubs, showers and P-traps under test, to a final once every fixture works.

Condos and townhouses: strata approval and the City's multi-family rules
If your condo or townhouse is strata-titled, a renovation inside it needs two separate approvals: the strata corporation’s and the City’s.
Strata approval. Under the Standard Bylaws in the Strata Property Act (section 5), an owner needs the strata corporation’s written approval before altering a strata lot in a way that involves the structure or exterior of the building; chimneys, stairs, balconies or other things attached to the exterior; exterior doors, windows or skylights, or ones that front on common property; fences and railings around a patio, balcony or yard; common property inside the strata lot; or parts of the lot the strata corporation must insure. Section 6 requires written approval for any alteration to common property. The strata must not unreasonably withhold approval for a strata-lot alteration, but it can require you to agree in writing to take responsibility for the related expenses. A strata’s own bylaws can add further rules, for example on flooring or work hours; our guide to what renovations you can do in a condo covers those, and what to send your strata for a kitchen shows a typical approval package.
City permits. The City’s multi-family renovation permits page lists the in-suite work that needs a building permit: relocating walls, disrupting fire separations, and installing or replacing a bathtub or shower. Tub and shower replacements need a plumbing permit too, which the City says is to make sure the plumbing does not harm the building as a whole and that every pipe through a fire separation is properly firestopped. Removing or moving wood-framed partition walls needs a report from a professional structural engineer certifying they are not structural. The online application for a single strata unit asks for consent of strata where applicable, so the strata approval normally comes first.
Work beyond your own unit is a bigger step. For common areas, multiple units, exterior changes or added dwelling units, the City may involve registered professionals, sealed drawings and Planning Division or Engineering review, and suggests calling Planning (604-527-4532) before applying.
On QUAY’s side, strata paperwork is part of the job, not an extra. In a Yaletown condo bathroom rebuilt around a new tub (about $25K + GST), QUAY handled the strata renovation request and WorkSafeBC clearance as part of the contract. For one owner’s three condos in a North Vancouver highrise, we filed the strata in-suite alteration paperwork and tested for hazardous materials where the building required it on each project. Both are outside New Westminster, so treat them as examples of the process, not of local rules. For the whole condo picture, see our condo renovation service.
Older homes in Queen's Park: when a Heritage Alteration Permit applies
Queen’s Park is a Heritage Conservation Area. The City’s Queen’s Park Heritage Conservation Area page sorts every house there into one of two categories, and that category decides whether you need a Heritage Alteration Permit (HAP):
- Protected properties: an HAP is required for renovations to the front or sides of the house, or to the roof visible from the street, including changes to windows and doors. No HAP is required for interior alterations, paint colour changes, routine maintenance or exterior alterations at the rear. An HAP is also required for a laneway or carriage house, and demolition is permitted only in specific circumstances.
- Non-protected properties: no HAP is required to alter the existing house or to demolish it. An HAP is required for a new house and for a laneway or carriage house.
Where an HAP is needed, it comes first: the City says you apply for the building permit once the HAP has been approved, and applications are reviewed against the area’s design guidelines. Protection also brings an incentive. A Protected house may have floor space up to 70% of the lot area (0.7 floor space ratio) against 50% for Non-protected houses, which matters if you are planning an addition. The City confirms each property’s category through the Planning Division and offers free one-on-one meetings of up to an hour with an area planner for owners of Protected properties (604-527-4532).
Houses on the Heritage Register or under a Heritage Revitalization Agreement have their own levels of protection, which the Planning Division can confirm before you draw anything. The heritage tools in the City of Vancouver work differently, as our guide to renovating a heritage home in Vancouver explains.
Secondary suites: adding one or authorizing an old one
Secondary suites are permitted in most single detached houses in New Westminster, according to the City’s secondary suite permits page, but the City asks you to confirm the zoning with the Planning Division before making plans. Suites must meet the Zoning Bylaw, including its rules on size, parking and flood construction levels, and the BC Building Code. Plans are approved by the Building Division before the building permit is issued, and a tree permit is also required.
When a suite is added to an existing house, the City lists what will be reviewed for code compliance: access and entrances, ceiling height, window size and area, fire separations, heating and ventilation, electrical and gas systems, and smoke and carbon monoxide detection. It warns that significant upgrades may be needed and encourages owners to discuss them with their contractor or designer early.
A few points catch buyers and landlords out:
- Since July 6, 1998, the City has allowed one authorized suite per single detached house, and an authorized suite is one created with a building permit.
- Paying the City’s secondary suite utility charge does not mean a suite is authorized.
- Suites cannot be strata-titled, sold or used for short-term rentals; they can house family or long-term tenants.
- A suite in a duplex unit or townhouse, or a second suite in a house, may have to be removed rather than authorized.
If you are finishing a basement now and may want a suite later, the City suggests building in the expensive parts at the same time: interconnected hard-wired smoke alarms, 5/8-inch Type X drywall on the suite ceiling and shared walls, a fire-rated door on the furnace room and between the units, and bedroom windows that meet the minimum openable size. Our legal suite checklist walks through what usually has to change.
How permits fit into a renovation schedule and budget
Permit review happens before construction can start, so the cleanest schedule settles the scope and drawings first and orders long-lead materials while the applications are under review. These are the ranges QUAY publishes for New Westminster on our New Westminster, bathroom and basement pages:
| Project | QUAY’s published range and time | Permits it commonly involves |
|---|---|---|
| Complete kitchen | About $40,000–$80,000+ | Plumbing permit if the sink or fixtures move; building permit if walls move; Technical Safety BC, not the City, for electrical or gas work |
| Complete bathroom | Most fall in about $25,000–$45,000+; about 10 working days on site once materials are ready | In a condo or townhouse, replacing the tub or shower needs building and plumbing permits |
| Basement finishing (no suite) | About $35,000–$55,000; about 4–6 weeks of construction | Usually for structural changes, plumbing and electrical work |
| Mid-range basement renovation | About $55,000–$75,000 | As above |
| Legal basement suite | About $75,000–$100,000+; about 6–10+ weeks | Zoning check, building permit and tree permit, plus trade permits |
Every QUAY project is priced in a fixed-price proposal before construction, with permits and any strata approval coordinated during planning, and completed work carries our 365-day workmanship warranty. Changes during the build are priced and approved in writing first. Exact prices depend on the property, the scope and the finishes, which is why we price from a site visit rather than a per-square-foot rate.
New Westminster renovation permit FAQ
Do I need a permit to renovate a bathroom in New Westminster?
It depends on the building and the scope. In a condo, apartment or townhouse, replacing a bathtub or shower needs both a building permit and a plumbing permit. In any home, moving or adding fixtures needs a plumbing permit, while replacing CSA-approved fixtures in the same place does not. Any permit for electrical work comes from Technical Safety BC, not the City.
Who issues electrical permits in New Westminster?
Technical Safety BC. New Westminster is not one of the 10 local governments delegated to issue their own electrical or gas permits, so electrical and gas work in the city is permitted by the provincial safety authority. The City issues building, plumbing, hydronic heating, services and sprinkler permits.
Can I remove a wall in my New Westminster condo?
Only with a building permit and, first, your strata’s written approval if the wall is part of the structure or common property. For wood-framed partition walls, the City requires a professional structural engineer’s report certifying that the walls being altered are not structural.
Do I need a Heritage Alteration Permit to renovate in Queen’s Park?
Only if the house is in the Protected category and the work changes the front, sides or the roof visible from the street, including windows and doors. Interior work, paint colours, routine maintenance and changes at the rear do not need one. Non-protected houses do not need one for alterations.
Is a secondary suite allowed in my New Westminster house?
Secondary suites are permitted in most single detached houses, but the City asks you to confirm the zoning with its Planning Division first. A suite needs a building permit and a tree permit, and paying the suite utility charge does not make an existing suite authorized.
How long does a plumbing permit take in New Westminster?
The City says plumbing permit review takes a minimum of 48 hours after it receives a complete application, and longer when volumes are high, the project is complex or the application is inaccurate. A building permit must be issued first unless the work is plumbing only.
Ready to get started?
Tell us what you want to change in your New Westminster home or condo, and we will confirm which permits and strata approvals it needs before anything is built.
Book a discovery callRelated guides
- Renovation Permits in Burnaby: Which Projects Need One and How the City Reviews Them: the same question next door, where the City issues its own electrical permits.
- What Renovations Can You Do in a Condo? BC Strata Rules and Permits: strata bylaws, approvals and common property.
- Convert a Basement to a Legal Suite: What Has to Change (Checklist): ceilings, exits, fire separation and the rest.