How Long Does a Condo Renovation Take in Vancouver?

Table of Contents

Once construction starts, most complete condo kitchens take about 15 working days on site and most condo bathrooms about 10 working days. Full condo renovations we have published ran about six weeks (a move-in refresh near Science World), about seven weeks (two West End two-bedroom suites) and about two months (a two-level downtown loft). Before that clock starts, allow time for design and selections, which took about two weeks on several of our projects, and for strata approval, which depends on your building.

If you are planning a full suite, our condo renovation service in Vancouver covers the whole process from strata paperwork to handover. This guide breaks down where the weeks actually go, using real schedules from finished QUAY condos, so you can plan your move-out, your elevator bookings and your budget around a realistic date.

Condo renovation timelines by scope

Time on site depends mostly on how many rooms are involved and whether plumbing, walls or gas lines move. These are the on-site durations QUAY publishes for each kind of condo project:

ScopeTime on siteReal example
Complete condo bathroomAbout 10 working days once strata approval is in placeA Yaletown condo bathroom ran about three weeks, including three extra days to replace water-damaged drywall found behind the old tile (condo bathrooms)
Complete condo kitchenAbout 15 working days once approvals are in placeA Yaletown kitchen expansion and bathroom were planned together on a 17-working-day schedule (project)
Small one-bedroom refreshAbout three to four weeksTwo North Vancouver units in the same highrise: about three weeks (2020) and about four weeks (2021) (project)
Move-in refresh, about 1,000 sq. ft.About six weeksTwo bathrooms, new counters on the existing cabinets, popcorn ceiling removal, lighting and paint near Science World, 2022 (project)
Full two-bedroom renovationAbout seven weeksWest End suite with the solarium wall removed, 2024 (project)
Full renovation, two-level loftAbout two monthsDowntown loft near Gastown, late April to end of June 2021 (project)

These are on-site times. The full calendar from your first call to move-back-in day is longer, because the waiting in a condo happens before demolition: design, strata approval and material lead times.

Stage-by-stage condo renovation timeline

Here is how a QUAY condo renovation is sequenced, with the durations from our published projects. Where a stage has no fixed length, we say so rather than guess; your proposal sets the full schedule for your suite.

StageTypical timeWhat happens
1. Discovery call and proposalSet by your projectWe review the suite, the rooms and your timing, then give you a fixed-price proposal before construction begins.
2. Design and selectionsAbout two weeks on our Science World and 2023 North Vancouver projects; a few weeks on the West End two-bedroomFinishes, fixtures and cabinetry are chosen so materials can be ordered before anything is torn out.
3. Strata approvalDepends on the buildingWe prepare the alteration request, insurance and WorkSafeBC documents during design. On our Yaletown kitchen the strata approved the request in October 2024 and work started in November 2024.
4. City permits (if your scope needs them)Depends on scopeOn our downtown loft, changing the bathrooms and adding a gas fireplace meant plumbing and gas permits. We confirm what your scope needs during planning.
5. DemolitionTwo to three daysTwo days near Science World; three days on the West End two-bedroom.
6. Rough-ins, waterproofing and drywallLate May on the West End two-bedroom (the first two weeks or so after demolition)Plumbing and electrical rough-in, shower waterproofing, drywall and cabinet installation.
7. FinishesJune to July on the West End two-bedroomTile, countertops, flooring, appliances, paint, lighting and blinds.
8. Walkthrough and handoverFinal daysDeficiency review, cleaning, documentation and handover, backed by our 365-day workmanship warranty.

Real QUAY condo schedules, week by week

Near Science World: about six weeks on site

This 1,000 sq. ft. condo got two refreshed bathrooms, new quartz counters on the existing kitchen cabinets, popcorn ceiling removal, new lighting, blinds and paint for about $58,000 + GST. The proposal was signed in May 2022 and selections were finished in a two-week design phase, so materials were ordered before demolition. We filed the strata alteration application, the owner signed the strata agreement and we posted the notice of project for neighbours. Demolition started June 2 and took two days, countertops went in on June 21, and the suite was finished July 12, 2022. See the Science World project.

West End two-bedroom: about seven weeks on site

Specifications and shop drawings came first in spring 2024, along with the building’s alteration request and indemnity agreement, our insurance and our WorkSafeBC clearance. Demolition in mid-May took three days. Late May covered rough-ins, drywall, cabinets and shower bases; June covered tile, quartz, flooring and appliances; paint, window frames and blinds wrapped up in July. The budget was about $178,000 + GST. See the West End project.

West End sub-penthouse: about seven weeks, with hazmat testing

In this roughly 29-year-old building, the strata application, hazmat testing and neighbour notices came before demolition on March 19, 2024. The renovation, including a waterfall-island kitchen, two walk-in showers and an expanded laundry, was completed in May 2024 for about $188,000 + GST. See the sub-penthouse project.

Downtown loft: about two months, with permits

Because the bathrooms and the gas fireplace changed, we pulled plumbing and gas permits as well as preparing the strata request. Construction ran from late April to the end of June 2021 for this two-level loft, about $163,000 + GST. See the loft project.

What strata approval adds to the schedule

Strata approval is separate from any City permit, and it is usually the first thing that can hold up a start date. Under the Standard Bylaws under the BC Strata Property Act, an owner needs the strata corporation’s written approval before altering parts of a strata lot that involve the building’s structure, exterior, common property inside the lot, or anything the strata must insure (Standard Bylaw 5), and before altering common property (Standard Bylaw 6). The strata must not unreasonably withhold approval under bylaw 5, but it can make you take responsibility for the alteration’s expenses. Many buildings have their own bylaws that replace or add to these, so read yours.

How long approval takes depends on how often your council meets and what it asks for. Under the Standard Bylaws a council meeting can be called on one week’s notice, but your building’s bylaws and meeting schedule decide the real wait. Vancouver stratas commonly ask for:

  • a written alteration request with drawings or a scope description
  • proof of the contractor’s insurance and a WorkSafeBC clearance
  • flooring and underlay specifications; one Yaletown building required an acoustic underlay rated IIC 73 and STC 72 (see what strata allows for condo flooring)
  • elevator bookings and work hours; the same Yaletown building limited elevator use to four-hour bookings between 9:30 a.m. and 4 p.m.
  • an indemnity agreement, a hazmat report or a renovation deposit in some buildings

The way to keep strata approval off the critical path is to prepare the application during design rather than after it. That is how we run every condo project; our strata renovation approvals page explains what we prepare.

Do you need a City permit, and does it add time?

The City of Vancouver says renovations, minor and major, will likely need approvals to make sure the work meets current bylaws and building safety, and that simple residential renovations under $250,000 can use its Residential Renovation Fast Track, which it says issues permits within a week (eligibility depends on the City’s criteria). On our condo projects, permits have followed the trades that change: the downtown loft needed plumbing and gas permits because its bathrooms and fireplace changed. We confirm what your scope needs during planning, before anything is ordered. For a project-by-project breakdown, see which renovations need a permit in Vancouver.

What makes a condo renovation take longer

  • Hidden damage. Water damage behind old tile added three days to our Yaletown condo bathroom. We price and approve any change in writing before the work happens.
  • Hazardous materials. Older buildings can need hazmat testing, and sometimes abatement, before demolition, as on the West End sub-penthouse and one of the North Vancouver units.
  • Building logistics. Elevator windows, quiet hours, loading-bay access and plumbing shut-downs set the pace of deliveries and debris removal.
  • Layout and structure. Removing a wall or bulkhead in a concrete highrise means checking what is behind it first; some hide structure, ducts or shared plumbing that must stay.
  • Late material decisions. Choosing finishes before demolition is what let the Science World suite finish in about six weeks. Changes after work starts add time and cost.

Can you stay in your condo during the renovation?

It depends on the scope, which utilities stay on, dust control and safety. A single bathroom in a two-bathroom suite is very different from a full renovation where the kitchen and both bathrooms are out of service at once. We talk this through during planning so you know before demolition whether to book somewhere else, and for how long. If only one room is being done, see how long a bathroom renovation takes or our kitchen renovation timeline.

How the timeline connects to cost

Longer schedules usually mean bigger scopes, not slower crews. Our published condo projects show the pattern: about $58,000 + GST for a six-week refresh, about $163,000 + GST for a two-month loft, and about $178,000 to $188,000 + GST for seven-week full West End renovations. For ranges by room and what drives them, read how much a condo renovation costs in Vancouver and condo kitchen renovation costs from four QUAY condos. Hiring someone new? Here is how to vet a condo contractor, and some condo renovation ideas to plan around.

Condo renovation timeline FAQ

How long does a condo renovation take in Vancouver?

On site, most complete condo kitchens take about 15 working days and most condo bathrooms about 10 working days. Full condo renovations QUAY has published took about six weeks to about two months on site, after design, selections and strata approval.

How long does strata approval take for a condo renovation?

It depends on the building, its bylaws and how often council meets. On QUAY’s Yaletown kitchen project the strata approved the request in October 2024 and work started in November 2024. We prepare the application during design so it does not delay the start.

How long does a condo kitchen renovation take?

Most standard condo kitchens take about 15 working days on site once approvals are in place. A Yaletown kitchen and bathroom done together were planned on a 17-working-day schedule.

How long does a condo bathroom renovation take?

About 10 working days on site for a typical condo bathroom once strata approval is in place. Hidden water damage can add time; one Yaletown bathroom ran about three weeks, including three extra days for damaged drywall.

Can my strata refuse a renovation?

Under Standard Bylaw 5 of the BC Strata Property Act, the strata must not unreasonably withhold approval for alterations to a strata lot, but it can require you to take responsibility for the alteration’s expenses. Your building’s own bylaws may differ, so check them first.