Bathroom Renovation Checklist: 12 Decisions in the Right Order
By QUAY Construction · November 25, 2026 · Bathroom
Quick answer: Make bathroom decisions in the order the room is built. Settle the scope and budget first, then check permits and strata approval, then fix the layout, the shower and its waterproofing, the vanity, the valves and fixtures, the tile, the lighting, the fan and the glass, and order everything before demolition starts. With QUAY, complete bathrooms commonly begin around $25,000, and many take about ten working days on site once those decisions are made and the materials have arrived.
This is the sequence we follow at our bathroom renovation service in Vancouver, written as a checklist you can use whoever builds your bathroom. Each step says what to decide, why it has to happen at that point, and which guide goes deeper. The order matters more than most people expect: a vanity chosen after the plumbing is roughed in, or a niche decided after the walls are waterproofed, means rework, delays or a compromise you live with for years.
The checklist at a glance
| # | Decision | Settle it | Go deeper |
|---|---|---|---|
| 1 | Scope and budget | Before design starts | Bathroom cost guide |
| 2 | Permits and strata approval | Before the layout is final | Bathroom permits in Vancouver |
| 3 | Layout and fixture locations | Before anything is ordered | Walk-in shower vs tub |
| 4 | Shower or tub, and the waterproofing system | Before tile is chosen | Shower waterproofing systems |
| 5 | Vanity and storage | Before the plumbing rough-in | Custom vanities |
| 6 | Valves, faucets and toilet | Before the plumbing rough-in | Walk-in shower installation |
| 7 | Tile, niches and transitions | Before ordering | Ideas from real QUAY bathrooms |
| 8 | Lighting, outlets and mirrors | Before the electrical rough-in | Electrical permits |
| 9 | Ventilation | Before the electrical rough-in | This guide, step 9 |
| 10 | Shower glass | During design; measured after tile | Bathroom renovation timeline |
| 11 | Ordering everything | Before demolition | Bathroom renovation timeline |
| 12 | Construction sequence and handover | Before you sign | Questions to ask a contractor |
Before design: scope, budget and the rules
1. Decide the scope and set a budget
Start by deciding what kind of project this is. A refresh (new vanity, fixtures, paint) and a complete renovation (taken back to the walls, new waterproofing, tile, plumbing fixtures, lighting and ventilation) are different budgets and different schedules. As our bathroom service page puts it, a $5,000–$10,000 budget usually covers smaller updates such as a vanity, fixtures or paint, while complete bathrooms commonly begin around $25,000.
For a complete bathroom, our bathroom renovation cost guide uses these planning ranges:
- Small, up to about 45 sq. ft.: $25,000–$35,000+ (powder rooms, compact condo and secondary bathrooms)
- Medium, about 45–75 sq. ft.: $30,000–$45,000+ (most primary and family bathrooms)
- Large, about 75+ sq. ft.: $40,000–$70,000+ (double vanities, large walk-in showers, freestanding tubs)
Real projects sit inside those ranges. Our Richmond condo bathroom kept its layout and came to about $24,000 + GST; our Coquitlam bathroom, where the tub became a walk-in shower with a custom 54-inch vanity, came to about $26,000 + GST. The single biggest lever is the layout: keeping fixtures where they are and choosing practical finishes keeps a complete project closer to the lower end. Our post on real bathroom renovation budgets breaks down eight QUAY projects.
2. Check permits and strata approval
Rules come before design because they decide what a layout change costs in time. In the City of Vancouver:
- A plumbing permit is needed to install, change or upgrade any part of a plumbing system. Repairing or replacing fixtures that stay in the same location does not need one.
- An electrical permit is needed for all electrical work, except replacing defective fuses, receptacles, switches or bulbs with units of similar type and rating.
- The City lists renovations that move interior walls or existing plumbing, electrical or gas lines as projects that need a permit, while replacing fixtures, cabinets or flooring and painting usually do not.
In a condo or townhouse, strata approval is a separate step from any City permit. Under the Strata Property Act’s Standard Bylaws, an owner must get the strata corporation’s written approval before altering a strata lot in ways that involve the structure of the building, common property inside the strata lot, or parts of the lot the strata corporation must insure. Your building’s registered bylaws may add to this, so read the alterations section early. Technical Safety BC also notes that strata owners cannot get a homeowner electrical permit and must hire a licensed contractor. Other municipalities run their own permit offices; our guide to bathroom permits in Vancouver goes through each type of work.
Design: the decisions that fix where pipes and wires go
Steps 3 to 10 are the design phase. Most of them have one thing in common: they set the position of a drain, a supply line, a valve, a box or a fan duct. Those positions are built into the walls and floor during the rough-in, weeks before you see a finished surface, so they have to be settled first.
3. Fix the layout and fixture locations
Decide where the toilet, vanity, shower or tub will sit. Keeping them in place is the cheapest and fastest route; moving one changes the plumbing system, which brings a plumbing permit and more work. Small adjustments still count: on the Richmond project the layout stayed, but QUAY moved the plumbing lines so the new sink and faucet sit where they should.
This is also the moment to settle the biggest choice in most bathrooms, tub or shower. Our guide to choosing a walk-in shower or a tub covers the trade-offs. If anyone in the household may need easier access later, plan it now; our aging-in-place bathroom checklist covers curbless showers and grab bars.
4. Choose the shower or tub and its waterproofing system
Most bathroom problems start behind the tile, which is why QUAY plans waterproofing, drainage and ventilation before any finishes go in. Decide the shower type (alcove tub, tub with a glass panel, walk-in shower on a sloped base, curbless) and the waterproofing system that goes with it. For tiled showers QUAY standardizes on Schluter; our comparison of shower waterproofing systems explains the alternatives.
Two examples show what this decision includes. In Coquitlam, the tub was replaced with a walk-in shower on a custom tile-ready Schluter shower base, with waterproof tile backer on all wet walls and Schluter waterproofing around the shower. In Richmond, the new tub walls got DensShield board and Schluter waterproofing before the tile went up. See our walk-in shower installation page for how a full shower is built.

5. Choose the vanity and storage
The vanity sets the height and position of the drain and supply lines, so choose it (or at least its width, sink type and faucet position) before the plumbing rough-in. Decide on storage at the same time: drawers or doors, a medicine cabinet, open shelves. QUAY designs custom vanities, built by our partner millwork shop, from about $3,000. In Coquitlam, a custom 54-inch wood-grain vanity with a quartz top sits under a custom mirrored medicine cabinet; in Richmond, a 36-inch sage green vanity with a marble-look top replaced a long builder-grade unit. Custom pieces go through shop drawings, so they need the most lead time of anything in the room.
6. Pick the valves, faucets and toilet
Shower and tub valves are built into the wall at the rough-in, and the visible trim has to match the valve behind it. Choose the shower system (single valve, rain head, handheld on a slide bar), the faucet and the toilet before the plumber starts. The Coquitlam shower has a rain head, a handheld on a slide bar and a single valve; Richmond has a new tub valve and hand shower and a Toto one-piece toilet. A wall-hung toilet is a design-stage decision too: it needs a concealed in-wall tank, new framing and backing, and usually a drain relocation, as in two of our North Vancouver townhouse bathrooms.
7. Select tile and plan niches and transitions
Tile is where most people want to start, but it comes after the layout and shower are fixed, because the shower type decides where tile goes and how floors slope. Settle the field tile, the floor tile, the height of tile on each wall, the position of any recessed niche (it sits inside the wall, so it is framed and waterproofed before tiling) and how edges, corners and thresholds finish. QUAY resolves these before installation and plans grout lines in advance. Richmond’s marble-look porcelain runs to the ceiling with a recessed niche; Coquitlam uses large-format marble-look tile floor to ceiling in the shower. For more looks from finished rooms, see bathroom renovation ideas from 13 real QUAY projects.

8. Plan lighting, outlets and the mirror
Lighting and power are roughed in with the plumbing, so every box has to be located before the walls close. Decide on ceiling lights, sconces or a lit mirror, the receptacle by the vanity, and extras such as in-floor heat. In Richmond, a black-framed mirror and two brass sconces replaced a wall-to-wall mirror; in Coquitlam, the electrical scope was new lighting, a fan, a switch and a GFCI receptacle. In Vancouver, all of this is electrical work that needs a permit unless it is a like-for-like replacement of a defective fuse, receptacle, switch or bulb.
9. Plan the ventilation
A bathroom fan is easy to treat as an afterthought, but it is part of the moisture plan that protects the waterproofing and finishes. Decide where the fan goes and how it is switched at the same time as the lighting, so the duct route and wiring are part of the rough-in. On QUAY bathrooms, ventilation is planned with lighting and receptacles rather than added at the end.
10. Choose the shower glass
Choose the style during design (a fixed panel, a hinged frameless enclosure or a sliding door), because it affects the shower curb, the threshold and where tile stops. The glass itself is measured once the tile is finished. As our North Vancouver project page notes, custom glass shower enclosures usually take around three weeks to fabricate and are installed shortly after the tile is done, so expect the glass to arrive a little after the rest of the room. Richmond got a fixed 10 mm glass panel with brushed nickel hardware; Coquitlam a custom frameless enclosure.

Ordering: get everything on site before demolition
11. Order everything before demolition
Once selections are final, order all of it: tile, vanity, fixtures, valves, toilet, lighting, fan and accessories. The rule we follow is simple: the bathroom is not opened up until the materials are ready, so the room is never sitting gutted while a box of tile is on its way. On the Richmond project, materials were ordered before demolition, which is why the bathroom work took 11 working days on site, from April 2 to 16, 2025. Many complete bathrooms take about ten working days on site; a larger ensuite runs longer. Our guide to how long a bathroom renovation takes has the on-site durations of eight QUAY bathrooms.
Construction and handover
12. Agree the construction sequence and handover
Before you sign, ask how the work will run and what you will get at the end. On a QUAY bathroom, you receive a detailed, fixed-price proposal before construction starts, and any change is priced and approved in writing before the work happens. On site the sequence is the same every time:
- Site protection and demolition
- Plumbing and electrical rough-ins
- Inspections, where permits apply
- Waterproofing and tile
- Vanity and millwork
- Fixture installation and finishing
- Final walkthrough, deficiency review and project documentation
Completed work is backed by a 12-month (365-day) workmanship warranty. If you are comparing contractors, our list of questions to ask a bathroom contractor shows what good answers look like.
Extra items for a condo or townhouse
A condo bathroom has the same twelve steps, plus building logistics that add time and planning. Our cost guide lists the items that come up most in strata buildings:
- Strata renovation approval in writing, before work starts
- Elevator bookings for demolition and deliveries
- Protection of common areas
- Restricted work hours and noise rules
- Plumbing shut-downs coordinated with the building
- Material delivery procedures and waste removal requirements
Strata approval usually depends on when council meets. On two QUAY condo projects, the West End strata approved two bathrooms in September 2024 and demolition started in mid-October, and the Yaletown strata approved in October 2024 with construction in November. QUAY prepares the renovation request and supplies documents such as an insurance certificate and a WorkSafeBC clearance. Our guide to condo bathroom renovation costs covers stacks, strata and real budgets.
Five mistakes in the order of decisions
- Starting demolition before materials arrive. It is the most common way a two-week bathroom becomes a six-week one.
- Choosing the vanity after the rough-in. A different width, sink or faucet position means moving lines that are already in the wall.
- Deciding the niche or shower bench late. Both are framed and waterproofed before tile; adding one later means opening finished work.
- Moving fixtures without allowing for permits. A layout change brings a plumbing permit and often electrical work, which adds review time before work starts.
- Leaving strata approval to the end. In a condo, the start date depends on council’s schedule, not just yours.
Printable bathroom renovation checklist
Bathroom renovation checklist: FAQ
What should I do first when planning a bathroom renovation?
Decide whether it is a refresh or a complete renovation and set a budget, then check permits and, in a condo or townhouse, strata approval. Only then fix the layout and choose finishes. With QUAY, complete bathrooms commonly begin around $25,000.
What order does a bathroom renovation go in?
Design comes first: layout, shower and waterproofing, vanity, valves and fixtures, tile, lighting, ventilation and glass. Then everything is ordered. On site the order is protection and demolition, plumbing and electrical rough-ins, inspections where permits apply, waterproofing and tile, vanity and millwork, fixtures and finishing, and a final walkthrough.
How long does a bathroom renovation take?
Many complete bathrooms take about ten working days on site once planning, selections and ordering are done. QUAY’s Richmond condo bathroom took 11 working days. Larger ensuites take longer, and custom shower glass usually takes around three weeks to fabricate after the tile is finished.
Do I need a permit to renovate a bathroom in Vancouver?
It depends on the work. In the City of Vancouver, replacing fixtures in the same location does not need a plumbing permit, but installing, changing or upgrading any part of the plumbing system does. All electrical work needs a permit except like-for-like replacement of defective fuses, receptacles, switches or bulbs. Moving interior walls also needs a permit.
How much should I budget for a complete bathroom renovation?
QUAY’s planning ranges are $25,000–$35,000+ for small bathrooms up to about 45 sq. ft., $30,000–$45,000+ for medium bathrooms of about 45–75 sq. ft., and $40,000–$70,000+ for large bathrooms. A $5,000–$10,000 budget usually covers smaller updates such as a vanity, fixtures or paint.
Ready to get started?
Tell us about your bathroom, your building and your timing, and we will walk you through how we would design, price and build it.
Book a discovery callRelated guides
- How Long Does a Bathroom Renovation Take? From Design to Handover: the on-site durations of eight QUAY bathrooms.
- Do You Need a Permit to Renovate a Bathroom in Vancouver?: which bathroom work needs a plumbing, electrical or building permit.
- Real Bathroom Renovation Budgets in Vancouver: 8 QUAY Projects: what complete bathrooms actually cost.